Summary:
On September 9th, 2026, at 12:20 AM PT, a system monitor alerted us of a backend system process exceeded its allotted runtime allocation and was therefore halted. At 3:51 AM PT, we received a customer report stating that Insights reports were not loading as expected. After initial triaging and troubleshooting, a platform incident was declared, and Insights Reports functionality was restored at 7:55 AM PT, with a backfill of missing reports data being completed at 8:25 AM PT.
Severity:
Sev-2
Scope:
Only customers on the Firstup EU platform were in scope of this incident. Customers on the Firstup US1 and US2 platform remained unimpacted.
Impact:
Studio users observed intermittent issues with loading data in Insights Reports.
Root Cause:
The root cause for this incident was determined to be process locks that were introduced by the addition of a new node in our data warehouse during the Software Release Maintenance window on September 8th, 2026. The new node cancelled currently running queries and left process locks on the primary data tables. Each subsequent process and transformation job that tried to run against the EU data warehouse instance was unable to complete due to the existing locks on those tables, which resulted in delays and incomplete data being presented in Insights Reports.
Mitigation:
To mitigate this incident, the process locks were manually cleared at 9:55 AM PT, stabilizing the tables and allowed new data to flow through, which restored the Insights Reports functionality. A data backfill task was also run to restore data that was missed during the incident, and Insights Reports were up to date as of 8:25 AM PT.
Recurrence Prevention:
To prevent such an incident from recurring, Firstup has committed to the following actions: